You don't have javascript enabled. Good luck with that.
Pencarian
Normalisasi Saluran Penghubung Malakasari Mencapai 450 Meter

Normalization on Jl. I Gusti Ngurah Rai PHB Channel Accelerated

PHB channel normalization on the north side of Jl. I Gusti Ngurah Rai, Malakasari, Duren Sawit, East Jakarta is keep accelerated.

We target to finish normalization in December. Now, 450 meters of it has been done

Recently, it has been normalized for 450 meters from total length 700 meters.

"Our target is to finish normalization in December. Now, 450 meters of it has been done," said Mustajab, Head of East Jakarta Water Resources (SDA) Sub-dept., Monday (9/11).    

Cipulir PPSU Personnel Cleaned Sekretaris River PHB

He explained, PHB channel normalization is started since March with retaining wall repairing, gabion wall installment, and trash and mud dredging.

"Its width is 3-4 meters. We are adding its depth 3.5 meters from before," he closed.

Linked News
Popular News indeks
  1. BMKG: Sunny to Cloudy Skies Forecast Across Jakarta Today

    access_time11-09-2026 remove_red_eye1724 personDessy Suciati
  2. Pramono Urges Jakmania to Keep Jakarta Safe

    access_time11-09-2026 remove_red_eye484 personDessy Suciati
  3. Pramono Endorses Five-City Tour for Jazz Goes to Campus

    access_time12-09-2026 remove_red_eye457 personDessy Suciati
  4. No Damage Reported Following Magnitude 5.9 Seribu Islands Quake

    access_time12-09-2026 remove_red_eye454 personBudhi Firmansyah Surapati
  5. Ketapang TPS 3R Processes 13 Tons of Waste from Duri Pulo and Petojo Utara

    access_time11-09-2026 remove_red_eye436 personFolmer